We’re building a 71-kilometre water pipeline between Bexwell and Bury St Edmunds.
It will eventually join up with the other planned pipelines to the north and south, forming the network that stretches from North Lincolnshire to Essex.
Update on works
As part of our updated programme, construction and reinstatement we will continue during the winter months, where conditions are suitable, from Bexwell to Bury St Edmunds.
Supporting works
We are building pumping stations at Bexwell, Kentford and Rede, as well as a storage reservoir at Rede.
Our impact
We continue to minimise our impact on communities and the environment, and work with local communities to deliver a legacy along the route.
If you would like to contact us about the Bexwell to Bury St Edmunds section of the project, please email strategicpipelines@anglianwater.co.uk.
| What We're Doing | What It Means | When It's Happening |
|---|---|---|
Building completed |
This is where we’ll be laying down the pipe, building pumping stations and storage tanks and connecting everything together. |
Late 2025 |
Restoring the land |
After building and testing the strategic pipe we’ll restore the land. |
Summer 2026 |
Commissioning date |
We test water quality and pressure-test the pipeline with full quality assurance. Once complete, the pipeline is sampled and prepared for connection to the water network. |
Late 2027 |
Building completed
This is where we’ll be laying down the pipe, building pumping stations and storage tanks and connecting everything together.
Late 2025
Restoring the land
After building and testing the strategic pipe we’ll restore the land.
Summer 2026
Commissioning date
We test water quality and pressure-test the pipeline with full quality assurance. Once complete, the pipeline is sampled and prepared for connection to the water network.
Late 2027